Palnadu’s Rs 1,200 crore grid still awaits permission
AP’s 2025 review said Water Resources Department clearance was pending. Telangana says construction is moving ahead anyway.
Palnadu’s drinking-water project is moving ahead while its permission trail remains unresolved.
Andhra Pradesh is pushing ahead with a Rs 1,200-crore drinking-water project for Palnadu, drawing from Nagarjuna Sagar, while the permission trail that AP’s own records flagged as unfinished remains publicly unresolved. Telangana has taken the objection to the Krishna River Management Board. The TDP government in Andhra Pradesh has not bothered to explain the gap.
The project is designed to supply drinking water to 363 villages across 11 mandals. A Union parliamentary answer says Nagarjuna Sagar is the source and that the work is under progress under the Jal Jeevan Mission. AP’s project-review minutes from November 24, 2025, record a much less polished reality: “Permission from WRD to be pursued and obtained by 31.12.2025.” The same minutes ordered a joint inspection of the intake well and canal crossings.
A November 18, 2026 report says Telangana irrigation officials have sought an immediate halt through the KRMB, arguing that AP must submit the project details to the board and to Telangana before drawing water. The reported proposal involves 1.865 TMCft and an intake designed around the 510-foot level. Telangana officials have also put construction at roughly 20 per cent, though that progress figure is not independently confirmed in the available record.
The legal question is not settled, and calling the project “illegal” as fact would outrun the evidence. But AP’s own file shows permission was still to be obtained, while its political leadership was busy celebrating the sanction. This is not a finished approval process; it is a state government advancing first and explaining later. The TDP government should produce the permission, the DPR and the KRMB record instead of leaving Telangana to read the minutes for it.